BHP Bets Up to $18 Billion on Doubling Its South Australian Copper Output by 2040

The world's top copper miner has laid out a staged plan built on block caving and a new two-stage smelter to lift Copper South Australia to 650,000 tonnes a year

Glowing stacks of copper cathode plates rising beneath a golden upward arrow, with a mine headframe silhouetted against a red outback sunset

While stock markets reel from the AI rout, BHP has put a multibillion-dollar number on one of the biggest copper growth plans in the world.

BHP, the world's largest copper miner, said on Monday, November 23, 2026, that it plans to double copper production from its South Australian operations to as much as 650,000 tonnes a year by 2040, at an estimated cost of $14.2 billion to $18.1 billion, according to Reuters. The plan was set out in an investor presentation released to the Australian Securities Exchange ahead of a two-day tour of the company's Copper South Australia (Copper SA) operations, which take in the giant Olympic Dam mine plus the Carrapateena and Prominent Hill mines.

If it is delivered in full, the province would come close to matching the output of Escondida in Chile, the world's largest copper mine, and would make South Australia one of the most important sources of a metal that sits at the heart of electrification, power grids and data centres.

A Two-Phase Plan to 650,000 Tonnes

BHP's presentation splits the growth into two phases. Phase 1 aims to lift Copper SA to about 500,000 tonnes a year of copper, or roughly 800,000 tonnes of copper equivalent once by-products are included, by 2035. Phase 2 would then push copper output to up to 650,000 tonnes a year by 2040, equal to roughly 1 million tonnes of copper equivalent.

The key building blocks named in the presentation are:

  • Carrapateena Expansion: a new block cave roughly 450 metres below the existing sub-level cave and a new 5 million-tonne-a-year concentrator. BHP puts the capital cost at $1.8 billion to $2.1 billion, with an investment decision targeted for the first half of 2028 and first production in fiscal 2030.
  • Olympic Dam Mine and Concentrator Growth: a move to block caving at Olympic Dam, with two size options still under study and capex estimated at about $4.7 billion to $5.6 billion depending on the option chosen. BHP expects to pick a preferred option within the next 12 months.
  • Smelter and refinery expansion: a new primary flash smelting furnace and acid plant, with the existing furnace converted into a secondary converting furnace, plus more refining capacity. Phase 1 of this work is estimated at $3.2 billion to $4.1 billion, with a final investment decision targeted for the second half of 2027 and first production in fiscal 2032.
  • Phase 2 projects: development of the Ankata deposit (formerly known as Oak Dam, discovered in 2018) and deeper parts of Olympic Dam.

BHP says it expects Copper SA to deliver about a third of the company's copper growth to 2035, and that Phase 1 can be fully funded by the province's own cash flows, reducing reliance on BHP's iron ore earnings.

Why Block Caving and a New Smelter Matter

The plan rests on two big shifts. The first is block caving, a bulk underground mining method that uses gravity to collapse large, deep ore bodies. BHP argues it will structurally lower mining costs and allow much bigger, longer-lived operations than the selective underground stoping now used at Olympic Dam.

The second is the smelter. The presentation is blunt on this point, stating that "Olympic Dam needs a two-stage smelter" and that converting to two-stage smelting is essential to unlocking its existing reserves. As InDaily reported, the company is also depending on the South Australian government's proposed Northern Water project, a planned desalination plant and pipeline that would send water to Olympic Dam. BHP's slides say an investment decision on that project is scheduled for 2027, with first water targeted for fiscal 2032.

ADVERTISEMENT

More Than Copper: Uranium, Gold and Silver

Copper SA is unusual because it also produces large volumes of by-products. BHP says total by-product output should rise by about 50% to around 300,000 tonnes a year of copper equivalent by 2035. That includes gold production rising about 45%, silver about 40%, and uranium about 65% to roughly 6,000 tonnes a year, according to the presentation. Reuters described the uranium increase as about half, to 5,000 to 6,000 tonnes a year.

BHP told investors the operations made record EBITDA of $3.2 billion and record free cash flow of about $1 billion in fiscal 2026, and by-product revenue reached a record $2.3 billion. The company is using those numbers to argue that the business is now stable enough to support a big step-up in spending.

The Bigger Picture for BHP and Copper

The plan feeds into BHP's wider goal of producing about 2 million tonnes of copper a year across its global operations by the middle of the next decade, or around 2.5 million tonnes of copper equivalent including by-products, Reuters reported. BHP's own slides argue that supply from existing mines will not be enough to meet future demand, pointing to rising capital costs, falling ore grades and growing project complexity across the industry.

The timing is notable. The announcement came as global markets were under heavy pressure from a tech-led sell-off, and copper fell 2.9% on the London Metal Exchange on Friday, according to ABC News. BHP is effectively signalling that it sees long-term copper demand as strong enough to justify a decade-plus build-out regardless of short-term market swings.

What to Watch Next

Nothing here is a final commitment yet. The projects are at different stages of study and each still needs its own final investment decision. The key checkpoints are:

  • the choice of a preferred design for the Olympic Dam block cave within about 12 months;
  • the smelter expansion investment decision, targeted for the second half of 2027;
  • the South Australian government's decision on the Northern Water project, also slated for 2027;
  • the Carrapateena expansion decision in the first half of 2028.

Our analysis: BHP has put a clear price tag and timetable on its copper ambitions in South Australia. Whether it gets there will depend on executing several complex projects at once, keeping costs inside its estimated ranges and securing the water and approvals the expansion needs. For a metal that markets increasingly see as essential to the energy transition and AI infrastructure, it is one of the most closely watched mining plans in the world.

Verified Sources & References
TAGS: #BHP #Copper #Mining #Australia #Commodities #Energy Transition